SCHEDULE.
Appendix V (C).
LOAN WORKS.
Additional Works to be charged to a proposed New Loan.
Works.
Revised Estimated Cost.
Revised Estimated Expenditure
Estimated Expenditur
1941-42.
1940-41.
C.
c.
C.
Head 1.-New Markets :-
(a) Central Market
*
50,000.00
11,771.33
Head 1.-Total .......
$ 50,000.00
11,771.33
I
Head 2.--Water Works.
(a) Supplies to Albany and
Peak Road
218,398.31
(b) Cross Harbour Pipes
833,009.53
25,000.00
(c) Rapid Gravity Filters,
Eastern
490,000.00
350,000.00
128,348.76
(d) Kowloon Chai Service
Reservoir and Pipelines (e) Distribution
490,000.00
299,480.27
220,000.00
86,164.50
26,358.80
(f) Shing Mun Valley
Scheme Catch waters (g) Rapid Gravity Filters,
1,070,000.00
420,000.00
63,781.43
Shing Mun Valley
Scheme
150,000.00
43,807.58
(h) Tai Lam Chung Valley
Scheme
150,000.00
88,042.36
20,000.00
(i) New Meters
250,000.00
100,000,00
56,315.62
(j) Waste Detection
225,000.00
80,000.00
90,743.23
(k) Miscellaneous Works
110,000.00
39,000.00
22,451.98
(1) New Workshop, Hong
Kong
100,000.00
15,000.00
85,000,00
Head 2.-Total
$4,306,407.84
$1,546,494.71 $ 492,999.82
Head 3.-Miscellaneous Works:-
(a) Extension of Aerodrome; Preliminary investiga- tion
60,000.00
58,879.68
Head 3.-Total
60,000.00 $ 58,879.68
Grand Total
$4,416,407.84
$1,617,145.72
$ 492,999.82
* Part Cost:--total cost is estimated at $910,126.10 of which $860,126.10 has been charged
to the 1934 Loan, Appendix V (b).